Planning a solar project above 500 kW in Egypt involves more than selecting panels and an EPC contractor. Before committing to a design or construction schedule, you need to understand the permits, technical studies and approvals that apply to your project.
The right route depends on who owns the plant, how the electricity will be used or sold, and how the system connects to the grid. This guide explains what to clarify first, which documents to prepare, and how to avoid gaps that can delay your application.
This practical roadmap includes activities that may run in parallel. Confirm the applicable sequence and allocate responsibilities through the project contracts and written authorisations. The owner and EPC actions below are suggested roles, not automatic legal duties.
1. Define the Project and Its Electricity-Use Arrangement
Start by clarifying who owns the plant, how the electricity will be used or sold, the proposed capacity, and the site and connection arrangements. These details determine which approval route needs to be assessed.
For the Project Owner: Confirm the ownership and electricity-use model, site details, and whether the project is a new installation or an expansion.
For the EPC Contractor: Prepare the preliminary layout, proposed DC and AC capacities, and connection concept.
How SPP Can Help: SPP reviews the project concept, identifies missing information, and helps map the studies, approvals and engineering support needed before detailed development begins.
Expected Output: A clear project brief and an initial roadmap for the next steps.
Check the implementing contractor qualification
Before appointing the installation contractor, verify its current New and Renewable Energy Authority (NREA) qualification certificate, registration and authorised capacity category against the proposed project. NREA publishes four categories:
- Bronze: up to 50 kW.
- Silver: up to 500 kW.
- Gold: up to 3 MW.
- Platinum: above 3 MW, within the qualification framework for capacities up to 20 MW.
These are the published kW/MW limits, not a universal project-capacity ceiling. Confirm the certificate's scope and rating basis with the relevant authority; do not relabel the limits as kWp or assume an AC/DC basis. NREA qualification requirements.
2. Coordinate with the Distribution Company or EETC
Engage the relevant distribution company or the Egyptian Electricity Transmission Company before treating the EgyptERA permit application as a standalone first step.
For distribution-connected net-metering projects, PV-Hub is the digital platform for project submission, registration and follow-up with the relevant distribution company. EgyptERA's Circular 4/2026 covers all distribution companies and net-metering applicants; inspections, technical approvals, metering and connection remain substantive steps. PV-Hub does not replace EgyptERA's applicable permit or licence. See the official circular and EEHC annual report in the sources below.
For the Project Owner: Establish the applicant and authorised contact; provide existing electricity-account and site information where relevant.
For the EPC Contractor: Support technical discussions and obtain the network information, connection requirements and study requirements needed for design development.
How SPP Can Help: Support technical coordination, organise submission inputs and track network-operator comments and outstanding requirements.
Expected Output: A documented connection pathway and the information needed to progress the required studies and approvals.
3. Complete the Grid Impact Study and Obtain Connection Approval
The Grid Impact Study (GIS) assesses network impacts, including voltage conditions, fault levels and power export. Its findings may require changes to the design.
For the Project Owner: Arrange the study and operator review, with clear responsibility for submissions and responses.
For the EPC Contractor: Supply design and equipment data and incorporate the resulting connection requirements into the project design.
How SPP Can Help: Prepare the Grid Impact Study, explain its design implications and support responses to technical review comments.
Expected Output: The required GIS, connection approval and supporting network-operator documents for the construction-permit file.
4. Prepare the Construction-Permit File and Obtain the Permit
Use EgyptERA’s current checklist, official forms and applicable Excel templates. Check names, capacities, locations and drawing revisions across the submission.
Key Requirements for the Construction Permit
- Company documents and authorisation of the applicant’s representative.
- Evidence of the right to use the project site.
- Project details, technical drawings and implementation schedule.
- Grid Impact Study and connection approval from the relevant distribution company or EETC.
- Feasibility study and project financing information.
- Applicable supporting documents, including electricity-supply agreements, the implementing contractor’s current NREA qualification certificate in the appropriate capacity category, and local-content approval, as required for the project.
- Completed official forms, required undertakings and evidence of payment of the applicable application fees.
Use EgyptERA’s current checklists and forms to confirm the complete requirements for your project.
Before submission, check that the applicant’s name, project location, capacity figures and design revisions are consistent across the entire package. Follow the official requirements for signatures, company stamps and supporting originals.
Official EgyptERA Checklists and Forms
For the Project Owner: Assemble corporate documents, site-use rights, authorisations, financing information, relevant agreements and required applicant declarations.
For the EPC Contractor: Prepare drawings, project details, the implementation schedule, grid documents and applicable installer-qualification and local-content inputs. Check that the NREA certificate and capacity category match the proposed project.
How SPP Can Help: Review submission readiness, coordinate technical and permitting inputs and track responses through the application process.
Expected Output: A complete application and, following the required review, the issued permit with its conditions recorded. Confirm the full requirements against EgyptERA’s checklist.
5. Complete the Environmental Assessment and Secure Approval Before Execution
The Environmental Impact Assessment (EIA) identifies potential environmental impacts and the measures needed to avoid or manage them. Start early, alongside other work where appropriate; do not wait for Step 4 simply because this section follows it.
For the Project Owner: Confirm the applicable environmental process and arrange the required assessment and approval before site execution.
For the EPC Contractor: Provide design and construction-method information and incorporate the required environmental measures into execution planning.
How SPP Can Help: Prepare the environmental assessment and help translate its requirements into practical design and construction actions.
Expected Output: The applicable environmental approval and implementation measures, with approval records retained for the generation-licence file.
6. Execute the Project and Maintain the Technical Records
Start work only when the construction permit and applicable commencement approvals are in place. Follow the approved design and conditions.
For the Project Owner: Establish oversight, change control and document-handover requirements before execution begins.
For the EPC Contractor: Maintain inspection records, equipment certificates, test reports and updated drawings; seek the necessary review of proposed changes before implementation.
How SPP Can Help: Provide Owner’s Engineer support through design reviews, site inspections and technical checks within the agreed scope.
Expected Output: An installed project with traceable construction and testing records. A construction permit alone does not authorise commercial operation.
7. Apply for the Generation Licence
Collect licensing documents during execution and submit using EgyptERA’s current checklist at the appropriate stage.
Key Requirements for the Generation Licence
- The construction permit and applicable construction licences.
- Company documents, site-use rights and authorisation of the applicant’s representative.
- Environmental-impact approval and grid-connection approval.
- Electricity-supply agreements, where applicable.
- Final project and equipment details, certified technical drawings, and the proposed organisational and management structure.
- Updated feasibility and financial information, including expected energy production.
- Completed application forms and evidence of payment of the applicable fees.
Confirm the complete requirements against the official checklist. The generation licence does not replace the network operator’s requirements for testing, energisation and connection.
Official EgyptERA Checklists and Forms
For the Project Owner: Assemble permits, environmental and connection approvals, corporate and site documents, relevant agreements, management information and updated financial inputs.
For the EPC Contractor: Provide final equipment and project details, certified drawings, expected-energy inputs and supporting technical records within the agreed scope.
How SPP Can Help: Review the licence package, coordinate technical documentation and help address submission gaps and authority comments.
Expected Output: A complete application and, following review, the generation licence. Network-operator requirements for testing, energisation and connection remain separate.
8. Complete the Distributor Agreement for the Approved Settlement Arrangement
For the practical route described here, return to the distributor after licensing to complete the applicable agreement and remaining commercial, metering and connection arrangements. Confirm project-specific timing; other agreements, including a producer-customer power-purchase agreement where applicable, may be required earlier. For a net-metering project, use the applicable EgyptERA-approved net-metering contract and annexes.
For the Project Owner: Confirm and sign the applicable agreement, including how generation, on-site consumption and permitted export will be metered and accounted for.
For the EPC Contractor: Support the metering and connection requirements and provide the final technical documents and outstanding agreed actions.
How SPP Can Help: Support testing and commissioning, review technical handover records and help track outstanding items before operational handover.
Expected Output: The applicable executed agreement, confirmed metering and settlement arrangements, and a record of any remaining conditions before operation.
Support from Project Review to Handover
From the first project review to final handover, SPP helps owners and EPC teams coordinate the studies, submissions and engineering oversight their project needs - with support tailored to the agreed scope.
Sources and Applicability
Reviewed on 25 October 2026. This article provides preparation guidance, not a project-specific regulatory determination. Above 500 kW describes the intended audience, not a universal regulatory trigger. The applicable route depends on the ownership, electricity-use and connection model; self-consumption or customer ownership does not automatically establish an exemption. Confirm current requirements with EgyptERA and the relevant authorities before submission.
The sequence is a practical roadmap, not a universal statutory signing order. Environmental assessment should begin early and may run alongside other approvals. Responsibilities depend on the project contracts, agreed scope and written authorisations. The requirement lists above are summaries, not substitutes for the full official checklists.
Official sources
- Construction-permit checklists and forms
- Generation-licence checklists and forms
- First-time construction-permit requirements, pages 2-3
- First-time generation-licence requirements, pages 2-3
- Circular 3/2026, including Articles 5 and 10
- Net-metering Circular 4/2026, Articles 1-2, 5 and 7, and Annex 1
- NREA installer qualification requirements and capacity categories, updated scheme approved 6 January 2025
- EEHC Annual Report 2023 2024, PV-Hub platform description